Cordial Cyber Castle is one of the popular Residential Developments in Technopark neighborhood of Trivandrum. It is among the Ongoing Projects of Cordial Developers and Builders Pvt Ltd. The landscape is beautiful with spacious Houses.
|
Amenities
* Fitness Centre with most modern equipment
* Jogging Track
* Jacuzzi
* Sauna and Steam Bath
* Multi-purpose Hall
* Provision for Snack Bar
* Fully furnished Air conditioned guest suites
* Children’s Park
* Children’s Play Area (Indoor)
* Badminton Court
* Card Room & Caroms Room
* Table Tennis Room
* Reading Room and provision for Reference Library
* Cyber Corner
* Provision for Children’s Creche and Day Care
* Internet connectivity provision for each apartment
* Elegant lobby with reception area
* Intercom facility
* Sewage Treatment Plant Backup generator for lifts
* Water pumps & common lighting
* Individual letter box and name board
* Changing room for drivers and cleaners
* Drivers/ Servants toilet
* 24 hrs security and water supply.
Specifications
* Flooring : Elegant Vitrified tile flooring for the entire apartment except toilets.
* Painting : Putty with acrylic distemper for internal walls and for ceiling. (Cornice in foyer, living and dining ). Painted finish for doors.
* Toilets : Anti skid Ceramic tiles for the floor, and glazed tiles for wall up to the door height. Sanitary fixtures matching with tiles. Geyser provision and health faucet in all toilets except servant’s toilet.
* Kitchen and work area : Counter with granite top and stainless steel sink. Glazed tiles above the counter to a height of 45 cms. Single bowl sink with granite top and provision for washing machine in the work area.
* Doors : Polished Teak wood entrance door. Moulded wooden panel doors for internal doors and toilets.
* Windows : Aluminium powder coated with glazed shutters and safety grills.
* Electrical : All wiring with power plugs. Adequate light and fan points. Points controlled by ELCB and MCB with independent KSEB metre. Modular switches.
* Generator : Generator backup for elevators, common lighting water pumps and designated points in each apartment.
* Elevators : Eight Numbers. Fully Automatic. (including 2 bed elevators)
* Cable TV : Connection in living and Master bedroom (subject to prevailing government rules)
* Telephone : Wiring for Telephone in Living and Master bedroom.
* Water supply : Water supply through sump and over head tank.
Air-Conditioning : Split AC provision in all bedrooms. Wired provision in master bedroom for fixing AC.
Fire Safety Features : Fire Protection systems as per rules.
Car Parking : Covered car parking (at extra cost.)
No bookings.
|
Work Status
***structural work - completed
***Block work - completed
***Elec chasin - completed
***Metal box fixing - completed
***GI Wire pulling - completed
***DB Dressing - completed
***Door frames fixing - completed
***Internal Plastering - completed
***Water supply piping - completed
***Internal plumbing - completed
***Toilet waterproofing - completed
***Floor tiling up to 15 th floor completed 14A,14C,14F,13C,13D,13E
Not done
***Toilet dadoing - up to 15th floor completed 14A,14C,14F,13C,13D,13E
Not done
***Electrical wiring up to 15th floor completed 14A,14C,14F,13C,13D,13E
Not done
***Wooden Doors upto10th floor completed
***Aluminum Windows up to10th floor completed
***Window grills up to 2nd floor completed
***False ceiling works up to 8th floor completed
***Cornice works up to12tth floor completed
***Balcony grills completed
***Kitchen granite 12th floor progress
***Kitchen dadoing 12th floor progress
***Painting primer In progress
***Painting first coat Not started
***Elec switches, etc Not started
***Sanitary fixtures Not started
***Elec testing Not started
***plumbing testing Not started
***Painting final Coat Not started
***Cleaning
kings tower top water tank work progress
***Kings tower External plastering work completed
***kings tower roof top parapit wall and oppen area parapit wall grill work progress
***Kings tower External 1st coat praimer work 90% completed
***Kings tower basement work progress
***Queens tower roof top parapit wall work completed
***Queens tower External plastering 70% completed
***Kings and Queens tower door polish work 30% completed
***Queens tower lift machine room & water tank work progress
***kings tower up to 10th floor common area and staircase tile work progress
***kings tower water tank for basement floor work progress
|
|